Husen Park improvements nearly complete
The boardwalk we wrote about early last summer, which will provide a viewpoint for Cedar Mill Falls, was delayed. THPRD decided last spring to have the property annexed into Beaverton. Once that transaction was completed, the city has been waiting for a "provider letter" from Clean Water Services certifying that the plans for the boardwalk will not adversely affect the wetland and stream. Hal Bergsma, Director of Planning for THPRD, says the city expects to receive that letter, "within the next couple of weeks. City approval should follow within a month or two. Then they will have to wait until the construction season, about April, to get started. They should be done by July 2011." The community will work with THPRD for a grand opening celebration.